RoofViews

Commercial Roofing

Roof to Wall Flashing: Why Details Matter for Single-ply Roofing Systems

By Karen L Edwards

August 06, 2021

Contractor working on a roof

Roof to wall flashing is critical to the performance of every single-ply roofing system. These transition points, where the flat part of the roofing system is tied into the parapet wall, are potentially vulnerable areas for water intrusion. Following the requirements for proper flashing can help ensure that the roof system offers better protection.

How do you install flashing on the wall and roof? Seasoned roofing industry professional Dave Scott of Roofing it Right with Dave and Wally talks through the various roof flashing methods and shares tips for success in a recent webinar.

High Wall Flashing with Screws and Plates

GAF Everguard™ TPO or PVC single-ply roofing systems require flashing between the flat roof surface and the adjoining wall. When using plates and fasteners, Dave refers to GAF detail 317C, High Wall Flashing with Plates and Fasteners.

EnergyGuard™ polyiso insulation should act as the base layer where the roof meets the bottom of the wall. The detail indicates that the insulation should not be greater than 8 inches. As Dave explains, "The reason you don't want the insulation to be thicker than 8 in. is because of the pendulum effect on your fasteners. As the sheet billows or moves, the fastener could lean, causing an egg shape in the hole, and your uplift resistance isn't what it should be."

Using Drill-Tec™ fasteners and plates, a reinforced membrane should be installed over the insulation, 12 in. on center. Another layer of reinforced membrane goes over that, extending up the wall and leaving a 6-in. lap on the roof so that it can be heat-welded into place. The membrane is attached to the wall using the fasteners and plates, again at 12 in. on center for base attachment.

Contractors have an alternate option for the base layer when installing roof to wall flashing: rather than using plates and fasteners, Dave says that opting for a termination bar is an option, as long as it is not higher than 3 in.

The next layer of membrane goes onto the wall, covering the first row of fasteners. Dave explains that up to 24 in. in height, the membrane can be dry hung on the wall. "If you are dry hanging the wall flashing, you are using a 30-in. sheet with a 6-in. lap. Basically, a 30-in. sheet is a half sheet, which is a 5-foot sheet cut in half. You'll have 30-in. flashings up the wall with a 24-in. reveal."

It is crucial to remember to use EverGuard Cut Edge Sealant on all cut edges of the reinforced TPO membrane.

High Wall Flashing with 10-ft. Wide Sheets

In detail 317A, Dave reviews the steps for high wall flashing using 10-ft. sheets.


The steps are similar to those of 317C: a base layer of EnergyGuard polyiso and then a layer of reinforced membrane, attached using fasteners and plates. With 10-ft sheets, the next step requires that EverGuard Bonding Adhesive be applied to the roof and the wall, followed by the installation of the 10-ft wide membrane.

Plates and fasteners get installed at the seam—vertically up the wall at 12 in. on center and a minimum of 10 ft. from any corner or end of wall. Laps are heat-welded, and the process continues until the wall flashing is complete.

"The maximum parapet wall height is not to exceed the width of a 10-ft. sheet," Dave notes. "You're going to have 6 in. on the deck, so on a 10-ft. sheet that gives you 9 [ft.], 6 [in.], so hopefully you can get over the top and install a cap."

A termination bar is acceptable at the top if the sheet is not able to go up and over, according to Dave.

High Wall Flashing with 5-Ft. Wide Sheets

Drawing 317B reviews requirements for high wall flashing with 5-ft. wide sheets of membrane.

It begins in a familiar way: with polyiso and membrane attached with fasteners and plates. The 5-ft. wide sheets are run vertically up the wall and attached with 12-in. on center fasteners also running vertically up the wall. Sheet laps are heat-welded, and the fasteners continue with vertical attachments spaced every 5 ft. along the wall.

Dave likes the versatility of the 5-ft. wide sheets. "The beauty of this is you can go as high as you want. If you have a 15-ft. wall, you can run a five-footer all the way to the top of that 15-ft. wall, and you don't need glue," he says.

Intermittent Fastening and Vertical Sheet Layout

Fastening patterns are key to the success of the system. Detail 317D shows the unique placement of the fasteners as well as how attachment plays a critical role at the corners and the ends of the building.

As Dave explains, "The first three sheets from each end of the building require a row of fasteners, 12 in. on center. Once you reach the interior corner, three sheets out from the corner each way also require the fasteners."

EverGuard cover tape or an 8-in. flashing strip should be installed over the fasteners. However, Dave notes that the fasteners being midway up the sheet make it conducive to using RhinoBond® to avoid penetrating the membrane.

Details matter when it comes to roof flashing. Fortunately, the experts at GAF are on hand to help you determine the best methods and find success. For more information on roof to wall flashing, register to view the full webinar. For additional courses and training opportunities, visit www.gaf.com/care.

About the Author

Karen L. Edwards is a freelance writer for the construction industry and has a passion for roofing, having worked in the industry for 20 years.

Related Articles

Conference attendees listen to a panel of speakers.
In Your Community

Making Connections at the 2024 GAF Latinos In Roofing Summit

For the past several years, GAF has hosted the Latinos In Roofing Summit & Expo to acknowledge, celebrate, and empower Latino roofing contractors and installers. The event provides networking opportunities, education, and training—presented entirely in Spanish—in a comfortable, welcoming atmosphere.Now in its third year, the summit has become a trusted resource for the Spanish-speaking contractor community to gain insights into how to better run and grow their roofing businesses. Educational sessions cover topics essential for business success, such as sales, insurance restoration work, commercial roofing, leadership, marketing, and roofing products.The first Latinos In Roofing Expo of 2024 was held on June 22nd in Los Angeles, and hundreds of industry professionals attended. With an emphasis on fostering community, the event featured a range of activities, including a pre-reception networking session and the chance to attend an LA Dodgers game with their new connections.Here's a look at what the event offered attendees and the experiences they shared.Breaking through Language BarriersAlan Lopez, GAF CARE trainer, explains that Latinos In Roofing events were developed when he noticed more Hispanic contractors attending GAF events conducted in English. For many of them, English was a second language, so it was harder to learn and take in all the information, some of which was lost in translation. Lopez reached out to his leadership at GAF, and they were eager to offer resources for Latino contractors, hosting the first expo in 2019.Abad Sarate, CEO of Asa Pro Roofing in Seattle, Washington, credits the conference being conducted entirely in Spanish as critical to successfully learning and understanding the information presented. "For us, it is very important to understand it in our main language, it is essential," he says. "And to have this type of conference for many Latino contractors fills us with pride." He continues, "I see more and more Latinos owning roofing companies, and the truth is that I am very happy—it makes me very proud as a Latino too."Luis Velasquez from Entrenando Latinos In Roofing agrees that the summit presented in Spanish was important to attendees' success. "We Latinos, who are first generation, who did not go through school, who come from poor countries, have a conflict and that is that we do not understand 100% English, we are not fully bilingual," he said. "So, when we manage to understand what is going on and how we can put it into practice, it is a complete gain. When we put knowledge in our head, the head will put money in our pockets."Creating an Annual Tradition for Roofing ProfessionalsGaining knowledge for business success was a key theme at this year's event. The informational sessions, keynote lectures, and demonstrations enabled attendees to learn about new products and gain new skills while connecting with other Latinos in the roofing industry. Many attendees were repeat visitors, demonstrating the value the event provides.Sarate is a two-time attendee and explains that the annual gathering has been instrumental in his company's development. "It has been an exceptional part of our growth because of all the knowledge that we take away from here," he shares. "We come back with much more knowledge. And in the end, knowledge is power... We put that knowledge back into the company, and it has benefited us a lot."Marcos Sierra from Sierra Group Roofing & Solar returned to the expo for a third time because of the networking opportunities and education. "The reason I come back is, one, to see my colleagues from other parts of the United States. Two, every time I come, I learn something new. And three, to refine, refine, refine. [So we can] grow our business," he said.Supporting Contractors beyond the Roofing Summit & ExpoThe Latinos In Roofing initiative started at GAF to create resources and a community for Spanish-speaking contractors and installers. Since establishing the initiative in 2017, the company has seen more and more members of the Hispanic community thrive.Contractors who attend the Latinos In Roofing Summit & Expo are granted access to GAF business tools, which they can use to raise their profit margins and reduce risks. They can also work toward becoming certified with GAF and joining the elite certified contractor program. They can then offer GAF warranties that help with their value propositions when working with potential clients.From increasing profits to growing their client lists and achieving financial independence, the contractors are finding success through the support they receive. Sarate can attest to how attending these Expos has helped his business. He notes that he's grateful for all of the support GAF offers.Joining the CommunityIf you're ready to become part of a community that truly understands your needs, will help you grow your business, and provide resources in your preferred language, explore GAF Latinos In Roofing. You can learn about available resources and online classes, join the GAF rewards program, become certified with GAF, and sign up to attend future events.

By Authors Karen L Edwards

September 18, 2024

Installation of ISO Board and TPO on a Roof
Building Science

Roof Insulation: A Positive Investment to Reduce Total Carbon

Have you ever thought about building products reducing the carbon dioxide emissions caused by your building? When considered over their useful life, materials like insulation decrease total carbon emissions thanks to their performance benefits. Read on for an explanation of how this can work in your designs.What is Total Carbon?Total carbon captures the idea that the carbon impacts of buildings should be considered holistically across the building's entire life span and sometimes beyond. (In this context, "carbon" is shorthand for carbon dioxide (CO2) emissions.) Put simply, total carbon is calculated by adding a building's embodied carbon to its operational carbon.Total Carbon = Embodied Carbon + Operational CarbonWhat is Embodied Carbon?Embodied carbon is comprised of CO2 emissions from everything other than the operations phase of the building. This includes raw material supply, manufacturing, construction/installation, maintenance and repair, deconstruction/demolition, waste processing/disposal of building materials, and transport between each stage and the next. These embodied carbon phases are indicated by the gray CO2 clouds over the different sections of the life cycle in the image below.We often focus on "cradle-to-gate" embodied carbon because this is the simplest to calculate. "Cradle-to-gate" is the sum of carbon emissions from the energy consumed directly or indirectly to produce the construction materials used in a building. The "cradle to gate" approach neglects the remainder of the embodied carbon captured in the broader "cradle to grave" assessment, a more comprehensive view of a building's embodied carbon footprint.What is Operational Carbon?Operational carbon, on the other hand, is generated by energy used during a building's occupancy stage, by heating, cooling, and lighting systems; equipment and appliances; and other critical functions. This is the red CO2 cloud in the life-cycle graphic. It is larger than the gray CO2 clouds because, in most buildings, operational carbon is the largest contributor to total carbon.What is Carbon Dioxide Equivalent (CO2e)?Often, you will see the term CO2e used. According to the US Environmental Protection Agency (EPA), "CO2e is simply the combination of the pollutants that contribute to climate change adjusted using their global warming potential." In other words, it is a way to translate the effect of pollutants (e.g. methane, nitrous oxide) into the equivalent volume of CO2 that would have the same effect on the atmosphere.Today and the FutureToday, carbon from building operations (72%) is a much larger challenge than that from construction materials' embodied carbon (28%) (Architecture 2030, 2019). Projections into 2050 anticipate the operations/embodied carbon split will be closer to 50/50, but this hinges on building designs and renovations between now and 2050 making progress on improving building operations.Why Insulation?Insulation, and specifically continuous insulation on low-slope roofs, is especially relevant to the carbon discussion because, according to the Embodied Carbon 101: Envelope presentation by the Boston Society for Architecture: Insulation occupies the unique position at the intersection of embodied and operational carbon emissions for a building. Insulation is the only building material that directly offsets operational emissions. It can be said to pay back its embodied carbon debt with avoided emissions during the building's lifetime.A Thought Experiment on Reducing Total CarbonTo make progress on reducing the total carbon impact of buildings, it is best to start with the largest piece of today's pie, operational carbon. Within the range of choices made during building design and construction, not all selections have the same effect on operational carbon.When making decisions about carbon and energy reduction strategies, think about the problem as an "investment" rather than a "discretionary expense." Discretionary expenses are easier to reduce or eliminate by simply consuming less. In the example below, imagine you are flying to visit your client's building. Consider this a "discretionary expense." The input on the far left is a given number of kilograms of carbon dioxide equivalent (CO2e) generated for the flight, from the manufacturing of the airplane, to the fuel it burns, to its maintenance. The output is the flight itself, which creates CO2 emissions, but no durable good. In this case, the only CO2 reduction strategy you can make is to make fewer or shorter flights, perhaps by consolidating visits, employing a local designer of record, or visiting the building virtually whenever possible. Now consider the wallpaper you might specify for your client's building. It involves a discretionary expenditure of CO2e, in this case, used to produce a durable good. However, this durable good is a product without use-phase benefits. In other words, it cannot help to save energy during the operational phase of the building. It has other aesthetic and durability benefits, but no operational benefits to offset the CO2 emissions generated to create it. Your choices here are expanded over the previous example of an airplane flight. You can limit CO2 by choosing a product with a long useful life. You can also apply the three Rs: reduce the quantity of new product used, reuse existing material when possible, and recycle product scraps at installation and the rest at the end of its lifespan. In the final step in our thought experiment, consider the insulation in your client's building. As before, we must generate a certain amount of CO2e to create a durable good. In this case, it's one with use-phase benefits. Insulation can reduce operational energy by reducing heat flow through the building enclosure, reducing the need to burn fuel or use electricity to heat and cool the building. The good news is that, in addition to the other strategies considered for the flight and the wallpaper, here you can also maximize operational carbon savings to offset the initial embodied carbon input. And, unlike the discretionary nature of some flights and the often optional decision to use furnishings like wallpaper, heating and cooling are necessary for the functioning of almost all occupied buildings.Based on this example, you can consider building products with operational benefits, like insulation, as an "investment." It is appropriate to look at improving the building enclosure and understanding what the return on the investment is from a carbon perspective. As the comparison above demonstrates, if you have a limited supply of carbon to "invest", putting it into more roof insulation is a very smart move compared to "spending" it on a discretionary flight or on a product without use-phase carbon benefits, such as wallpaper.This means we should be careful not to measure products like insulation that save CO2e in the building use-phase savings only by their embodied carbon use, but by their total carbon profile. So, how do we calculate this?Putting It to the TestWe were curious to know just how much operational carbon roof insulation could save relative to the initial investment of embodied carbon required to include it in a building. To understand this, we modeled the US Department of Energy's (DOE) Standalone Retail Prototype Building located in Climate Zone 4A to comply with ASHRAE 90.1-2019 energy requirements. We took the insulation product's embodied energy and carbon data from the Polyisocyanurate Insulation Manufacturers Association's (PIMA) industry-wide environmental product declaration (EPD).To significantly reduce operational carbon, the largest carbon challenge facing buildings today, the returns on the investment of our building design strategies need to be consistent over time. This is where passive design strategies like building enclosure improvements really shine. They have much longer service lives than, for example, finish materials, leading to sustained returns.Specifically, we looked here at how our example building's roof insulation impacted both embodied and operational carbon and energy use. To do this, we calculated the cumulative carbon savings over the 75-year life of our model building. In our example, we assumed R-30 insulation installed at the outset, increased every 20 years by R-10, when the roof membrane is periodically replaced.In our analysis, the embodied CO2e associated with installing R-30 (shown by the brown curve in years -1 to 1), the embodied carbon of the additional R-10 of insulation added every 20 years (too small to show up in the graph), and the embodied carbon represented by end-of-life disposal (also too small to show up) are all taken into account. About five months after the building becomes operational, the embodied carbon investment of the roof insulation is dwarfed by the operational savings it provides. The initial and supplemental roof insulation ultimately saves a net of 705 metric tons of carbon over the life of the building.If you want to see more examples like the one above, check out PIMA's study, conducted by the consulting firm ICF. The research group looked at several DOE building prototypes across a range of climate zones, calculating how much carbon, energy, and money can be saved when roof insulation is upgraded from an existing baseline to current code compliance. Their results can be found here. Justin Koscher of PIMA also highlighted these savings, conveniently sorted by climate zone and building type, here.Support for Carbon Investment DecisionsSo how can you make sure you address both operational and embodied carbon when making "carbon investment" decisions? We've prepared a handy chart to help.First, when looking at lower-embodied-carbon substitutions for higher-embodied-carbon building materials or systems (moving from the upper-left red quadrant to the lower-left yellow quadrant in the chart), ensure that the alternatives you are considering have equivalent performance attributes in terms of resilience and longevity. If an alternative material or system has lower initial embodied carbon, but doesn't perform as well or last as long as the specified product, then it may not be a good carbon investment. Another consideration here is whether or not the embodied carbon of the alternative is released as emissions (i.e. as part of its raw material supply or manufacturing, or "cradle to gate" stages), or if it remains in the product throughout its useful life. In other words, can the alternative item be considered a carbon sink? If so, using it may be a good strategy.Next, determine if the alternative product or system can provide operational carbon savings, even if it has high embodied energy (upper-right yellow quadrant). If the alternative has positive operational carbon impacts over a long period, don't sacrifice operational carbon savings for the sake of avoiding an initial embodied product carbon investment when justified for strategic reasons.Last, if a product has high operational carbon savings and relatively low embodied carbon (lower-right green quadrant), include more of this product in your designs. The polyiso roof insulation in our example above fits into this category. You can utilize these carbon savings to offset the carbon use in other areas of the design, like aesthetic finishes, where the decision to use the product may be discretionary but desired.When designing buildings, we need to consider the whole picture, looking at building products' embodied carbon as a potential investment yielding improved operational and performance outcomes. Our design choices and product selection can have a significant impact on total carbon targets for the buildings we envision, build, and operate.Click these links to learn more about GAF's and Siplast's insulation solutions. Please also visit our design professional and architect resources page for guide specifications, details, innovative green building materials, continuing education, and expert guidance.We presented the findings in this blog in a presentation called "Carbon and Energy Impacts of Roof Insulation: The Whole[-Life] Story" given at the BEST6 Conference on March 19, 2024 in Austin, Texas.References:Architecture 2030. (2019). New Buildings: Embodied Carbon. https://web.archive.org/web/20190801031738/https://architecture2030.org/new-buildings-embodied/ Carbon Leadership Forum. (2023, April 2). 1 - Embodied Carbon 101. https://carbonleadershipforum.org/embodied-carbon-101/

By Authors Elizabeth Grant

September 13, 2024

Roofers install GAF EverGuard® TPO Quick-Spray Adhesive on a flat roof
Commercial Roofing

Minimizing Disruption When Repairing Roofs on Schools and Hospitals

As a roofing contractor, you know how noisy roofing projects can get. And when repairing or replacing roofs on institutional properties, like schools and healthcare centers, it's often not possible to remove occupants during the project's duration.Accordingly, minimizing disruption at these facilities is key, as students need to be able to concentrate and patients must be protected as they recover. Here are common disruptions to consider and how to reduce them, with insight from GAF Building and Roofing Science Research Lead, Elizabeth Grant.Common Disruptions on Construction SitesYou have several challenges to consider when working on schools or other facilities with ongoing operations, including noise, odors, and occupants' safety.Elevated VolumeHeightened noise levels can affect both students and patients. At schools, loud sounds can affect students' ability to learn and concentrate. Likewise, construction noise can impact patients' ability to rest and recuperate in healthcare facilities.Strong OdorsWhen using certain roofing materials on big job sites—like powerful adhesives or hot-mopped roofing systems—odors may infiltrate the building. This may be distracting and affect the comfort of students and patients.Heavy MachineryUnloading and staging material can also cause disruption, as materials must be staged onsite to be ready for installation as the job progresses. This often involves using heavy equipment, such as cranes and lifts. Proper safety protections must be in place to ensure worker and occupant safety.Roofing Products That Minimize DisruptionUnfortunately, there's no good time for a roof repair or replacement at a medical facility. You may be able to complete school projects when school is out of session, but that isn't always the case if a leak or storm damage occurs.The best (and most proactive) way to minimize disruption is to use durable, long-lasting materials, as this reduces the number of times crews need to work on the roof.Single-Ply MembranesGrant recommends a robust single-ply membrane or a system with some redundancy, such as a multi-ply modified bitumen. She also suggests leveraging a hybrid system, composed of a multi-ply modified bitumen system with a single-ply top sheet for reflectivity.Cover and Substrate BoardsFor resiliency against noise-causing conditions such as hail and foot traffic, Grant suggests using cover and substrate boards. Cover boards are installed on top of the insulation and provide sound insulation, while substrate boards are installed directly on the roof deck under the insulation."If you have a really noisy location, and you want to keep people inside from hearing a lot of disruption, having cover and substrate boards included in the system can be really important," says Grant.Adhesives and FastenersAnother change you can make to reduce disruption is using adhesive to attach roofing products instead of mechanically fastening them. This helps avoid the noise from driving fasteners into the roof deck—and enables a faster installation.Grant notes that, depending on the FM and wind ratings required, it may be possible to adhere all the system components, including the insulation, cover boards, and membrane. An adhesive like GAF EverGuard® TPO Quick-Spray Adhesive can effectively adhere TPO and PVC roofing materials. The product has a high initial tackiness, allowing for faster installation than traditional adhesives. You can also opt for self-adhering products (vapor retarder, pipe boots, TPO roofing, etc.), which can further reduce installation time by eliminating adhesive application from the process.Materials That Shorten Project TimelinesA creative and efficient way to minimize disruption at school and hospital job sites is to reduce the time crews are on the roof. By taking advantage of time-saving materials, you can reduce the risk to workers and occupants, increase productivity, and ultimately take on more work.In addition to the Quick-Spray Adhesive, GAF offers several materials designed to cut installation time and labor:Wider rolls of TPO (12 feet instead of 10 feet) can help crews to spend less time installing systems on wide-open roofs.Insulation installation is easier with lightweight Ultra HD Composite Insulation, and it eliminates the need for one full application of adhesive in adhered systems.TPO self-adhered membrane can cut installation time by as much as 60% compared to installation using traditional bucket and roller adhesives.Experienced Support That Streamlines WorkIn addition to product and material selection, you can minimize disruptions by having GAF professionals from the Tapered Design Group help design the tapered insulation system. These professionals can help you with a variety of services, such as:Tapered insulation designTapered insulation Inventory management and orderingBudget friendly alternativesTapered insulation systems are designed to improve the drainage slope on roofs with substrate damage or without enough slope. The tapered design team at GAF "balances suitable slope with the least amount of material," Grant says. "To help with saving money, saving material, and saving time."This group designs tapered insulation systems that can be loaded and labeled strategically to minimize material handling and time spent looking for and transporting materials. Products are bundled by roof area, and a color-coded plan distinguishes areas for each bundle. Materials are precut and specifically designed for each project.Additional Tools to Save Time and LaborTwo other GAF tools can help you reduce the time spent on projects: GAF QuickSite™ and GAF QuickMeasure™.GAF QuickSite™GAF QuickSite™ provides the information you need before approaching a potential customer. It gives you a snapshot of local codes (important if you're working in an unfamiliar location), a 10-year wind and hail history, historical photographs documenting changes over time, and parcel information (including size and sales dates).GAF QuickMeasure™GAF QuickMeasure™ provides complete roof measurements including parapet wall lengths, heights and widths to help create estimates, past views showing how a roof may have changed over time, grid-lined paper for buildings with predominate pitch of 0 or 1, and a DXF file output for CAD.With the help of GAF QuickSite™, GAF QuickMeasure™, and the Tapered Design Group, you can confidently give your healthcare clients and school customers accurate estimates for suitable roofing products to meet their needs. These tools can also minimize disruption to building occupants and help building owners select durable, long-lasting products that will protect their investments for years to come.Leveraging GAF Professionals' ExperienceWhen working on schools, hospitals, and other important institutions, you're working to satisfy not only your clients but the individuals visiting these locations. By minimizing disruption, you can help ensure everyone involved experiences minimal disruption while you complete the project.For more insight into time- and labor-saving products and services, explore GAF School Rooftop Resources.

By Authors Dawn Killough

August 29, 2024

Don't miss another GAF RoofViews post!

Subscribe now